Thursday, 8 November 2018

Update on the Lagos Metro Railway - Photos


Aftermath of the postponement of the Lagos Metro Railway which is being funded by the Lagos State Government and the World Bank, the questions on the lips of Nigerians are are we going to abandon the project? Will the construction works stop? What will happen to Nigerians working on the site?

It was earlier reported that the Lagos State Government has announced that its light rail project running between Mile 2 and Marina will now commence passenger operation in 2022.

The mass transit rail project called the Blue Line awarded to China Civil Engineering Construction Corporation had suffered many delays due to paucity of funds and other challenges.

But the state government said that after a comprehensive review of the project, it had approved a roadmap proposed by its consultants to complete the civil infrastructure as well as the operation and maintenance infrastructure needed for the commencement of passenger operation in 2022.

“Following the report, Alstom SA France, who are experienced international railway systems aggregator and rolling stocks manufacturer, with over 100 years of railway experience covering 60 countries, was engaged to review the report of the consultant. Alstom SA agreed with the submission of the consultant that the first phase of the rail project could only become operational in 2022 based on proposed funding pattern,” it stated.

In its bid for investigative reportage, AutoReportNG was able to have access to some ongoing works at various site and we can confirm that work is going on at the Marina axis but at a slow pace. We also got the layout map for the bridge that runs through the Eko Bridge into Marina.

See more below...







Labels: , ,

Tuesday, 20 March 2018

A Pictorial View of Lagos Rail Mass Transit (LRMT) Construction


It's been almost 6 years since the Lagos Rail Mass Transit has started, the work started under the former Lagos state governor Mr. Babatunde Fashola, according to him then, the work will be finished before he leaves office in 2015 but due to logistics and funding, they were unable to meet with the deadline. During the campaign of Mr. Akinwunmi Ambode, he promised to finish up from where Mr. Fashola left and so far the work has been going slow and steady.

AutoReportNG did a self-media tour (if anything like that exists) and we start from CMS to Costain (National Theather, Iganmu, Lagos) and we were able to access some developments and see how the work is faring. These are some of what we gathered...

Contractor: The contract was awarded to China Civil Engineering Construction Corporation (CCECC) and they were in charge of all mechanical and other engineering works, so far the quality of the materials were top notched, kudos must be given to Lagos State Government who ensured that they compiled to safety guidelines and also who made sure they use quality goods as well.

Challenges: We were able to identify 2 major challenges during our short tip and this has to be the slow working process of the firm, for example working on the Eko Bridge is long overdue, they have been on that since last year and they are yet to leave the same spot and this call for concern, how many years will it take them to construct over the sea. Another challenge we see is the issue of the miscreants also known as area boys, they defaced most of their works, the placed that have been constructed have turned to a garage or their second home. A visit to Orile Bus Stop along Mile 2 will clear your doubts. We also noticed that the rail-lines have been messed up as some have turned the place to their toilets.

Funding: We were able to interact with some of the workers of the CCECC and we asked them why the slow pace despite the government fundings but the workers debunked that CCECC is not releasing money and also there is shortage of funds, whatever that means, its either LASG is not releasing money or CCECC is not paying its staff, you be the judge.

Safety: The CCeCC company are not security conscious at all, most times the edge of the pillar of the train and that of the other bridge as so closely held together that if you are new in this area you are likely to get confused, it is expected at least CCeCC puts up a warning sign to warn drivers ahead but we are surprised none of this exists not even in CMS a CBD centre. We appeal to LASG to mount pressure on them before we hear of stories that touch. Same scenario if you are on the bridge of Eko Bridge, the edges of both are too fitted together.

Completion Date: It will take a miracle for this project to be ready in 2019 as there are lots to be done, the dredging of the Eko Bridge for example still remains a top priority, many of the Train Stations have not been put into place, most of the rail lines still need some touches, we are aware that Mile 2 to Orile has been completed to a certain stage but they still need to be checked again. So ladies and gentlemen, brace up yourself.

If we are to rate the work and how they fared, we will rate them 52% except a miracle happens tomorrow morning.

These are the pictures we are able to take, we are not given access to enter the National Theatre Rail Terminus




























Labels: , , ,